Technical Assistance to Support the Implementation of the Crosscutting Justice Strategy in Albania (JUST – AL)

Technical Assistance to Support the Implementation of the Crosscutting Justice Strategy in Albania (JUST – AL)

 

Project Value 1,667,400.00 €
Project Status Ongoing
Implementing Partners

The German Foundation for International Legal Cooperation e.V. (IRZ)

Beneficiaries:

Ministry of Justice

EU Contribution
1,667,400.00 €
Project Timeline
06.2022 - 02.2025

Overall Objective

The overall objective is to strengthen the capacities of the Ministry of Justice and the independent justice institutions to implement the Cross-Sector Justice Strategy (CSJS) and its Action Plan.

Summary of the Project

The project aims at increasing the capacity of the MoJ in the management of CSJS, leading the coordination of justice policies and in setting and ensuring legislative drafting standards as well as communicating on developments in the justice sector.

Activities

Results

Component 1: Management of Strategic Planning

Activity 1.1.1.Needs Assessment and Capacity Building Plan;
Activity 1.1.2 Capacity Building for CSJS Management;
Activity 1.2.1. Update of CSJS;
Activity 1.2.2.  Budgeting CSJS Reviews;
Activity 1.3.1. Sublegal and Other Acts for Monitoring, Evaluation and Reporting Mechanism;
Activity 1.3.2 CSJS related documents;
Activity 1.4.1 Design and Modus Operandi of Coordination and Cooperation Mechanism;
Activity 1.4.2 Operation of Coordination and Cooperation Mechanism;
Activity 1.5.1. Consultation with Civil Society;
Activity 1.5.2. Donor Coordination;
Activity 1.6.1. Capacity Building for Staff of General Directorate of Codification;
Activity 1.6.2 Elaboration of Justice Related Legislation;
Activity 1.7.Final Report on Management, Planning and Budgeting Capacities.

Component 2: Monitoring and Reporting

Activity 2.1.1 Mapping of Needs regarding Data Collection, Analysis and Reporting and Capacity; Building Programme;
Activity 2.1.2 Capacity Building regarding Data Collection, Analysis and Reporting;
Activity 2.2.2 SoPs for Mechanism;
Activity 2.3 Final Report.

Component 3: Communication

Activity 3.1.1 Needs Assessment and Capacity Building Plan;
Activity 3.1.2 Capacity Building on CSJS Communication;
Activity 3.2.1. Communication Strategy;
Activity 3.2.2.Communication Plan;
Activity 3.3.1 Implementation of Communication Plan;
Activity 3.3.2. Evaluation of Impact of Implementation of Communication Plan;
Activity 3.4 Final Report.